Monday, February 9, 2015

New Photos From the Upper Floors

Below are some photos taken this morning of the construction.  They include interior views from the new 5th and 6th floors.  On the 5th floor only a very small portion of the old roof remains to be jack-hammered out once the last remaining windows are installed nearby -- special heavier windows for the frames that will span the height of both floors at the northeast corner of the building. The new mechanical system on the 5th floor is being set in its permanent location along the back of the building. All mechanical units have now been moved from their temporary location on the side of the building that will be the 5th floor stacks. On the 6th floor, drywall is being hung on wall frames, most columns are enclosed, and work may begin soon on the ceilings.


Click here for larger photos with captions or to view from a mobile device.