The scheduled dates for each closure phase are listed below:
- Women’s restrooms on the 3rd and 4th floors will be shut down Feb. 19 through April 16
- Men’s restrooms on the 3rd and 4th floors will be shut down March 17 through June 30
Restrooms on floors 1 and 2 should be unaffected. The smaller restrooms on the basement level at the foot of the former entrance stairs leading down to the staff and snack lounges will also still remain available.
During the first closure phase the women’s restrooms on the 3rd and 4th floors will be blocked off in order to remove the wall between them and the central stairwell. During the second phase the men’s restrooms on the same floors will be closed in order to remove the wall between them and the building’s central chase (a large hidden central air duct that is adjacent on the opposite side).