The reshelving process took just eight days and was accomplished by a small team of staff diverted from the Tulane Legacy Collection Analysis Project, which is identifying, examining for condition, and physically flagging the library's pre-1938 books stored off site, books that will eventually be among those housed in a new rare books area on a new 6th floor. The reshelvers--principally Kelsey Chapman, Katelyn Howells, and Izzy Oneiric--are employees of the library services firm LAC Group.
Books in preparation for freeze-drying |
In the 4th floor open stacks area, workers removed all the ceiling tiles and have been installing sprinkler pipe, roof drains, and, over the book stacks, motion sensors that will turn lights off and on in the aisles between each range. The sensors will dole out energy for lighting based on use of the aisles rather than simply leaving the lights on 24/7. Lights in broader access aisles or seating areas will have standard illumination. The ceiling work is expected to be completed in this area by the end of this week or early next, after which the plastic sheeting now covering the book shelves there will be removed.
Next, the same work will be repeated in an adjacent quadrant of the 4th floor and eventually will move sequentially throughout the building, although more limited in scope on the lower floors.
The contractor has completed the forms for the shear wall slab being built in the central stairwell and has poured concrete for about half the slab, with the rest to be completed this week. Nearby, another crew is removing walls between the men's restroom and the building's central chase to soon begin to build forms for a final shear wall there. Roof work has continued to remove a layer of rooftop“membrane” from a ten-foot wide swath around the roof perimeter. Workers are almost completely around the perimeter at this point and, basically, they have peeled the membrane back to where they are already constructing the base of what will be the outer wall of the library's new 5th and 6th floors. Steel for those floors should begin to arrive onsite very soon and erection of the steel frame will likely be accomplished in a concentrated and tightly phased time frame of about eight weeks.
No comments:
Post a Comment