Installation of the fire suppression sprinkler system on the 3rd floor is scheduled to begin on June 25. The work will progress through the floor in phases and the construction contractor’s dates for these phases are below. The floor chart to the right outlines the location of the work in each phase.Phase 1: (6/25 – 7/11)
Area location: northwest quadrant of the building
- Faculty carrels affected: F317-F327
- Grad student carrels affected: carrels in areas along the northwest wall of the building
Area location: southwest quadrant of the building
- Faculty carrels affected: F309-F316
- Grad student carrels affected: carrels in areas along the southwest wall of the building
Area location: southeast quadrant of the building
- Faculty carrels affected: F301-F308
Area location: northeast quadrant of the building
- Faculty carrels affected: F328-F332