1st Floor
Phase 4 Area: March 2 - March 20
Area location: northeast quadrant of the building
- Collections affected: Book stacks RC321.E94 - ZA9999
- Faculty carrels affected: F112, F113, F114
- Student areas affected : computer work stations in the Quiet Area
Area location: northwest quadrant of the building
- Collections affected: Books stacks QE1.A28 - RC321.E95
- Office areas affected: CLUE offices (125, 124, 123,123A), Head of Acquisitions office (126)
- Student areas: Media Room (119), group study rooms (120 and 121)
- Grad student carrels affected: carrels in areas 127V and 147V along the northwest wall of the building
2nd Floor
The schedule for the 2nd floor is very similar to the one announced previously, except a separate early period for working in the staffed areas of Microforms & Newspapers and Interlibrary Loan (ILL) has been omitted and rolled into the same dates as those for the adjacent Phase 3 area. Otherwise, the dates for work in the Phase 3 and Phase 4 areas are unchanged. The schedule does include some overlap between the 1st and 2nd floors in early April.
Area location: southwest quadrant of the building
- Collections affected: Book stacks QD1.T63 - QD951.W82
- Faculty carrels affected: F209-F216
- Phase 7 Area: Now to be concurrent with Phase 3
- This is the area in southwest quadrant of the building limited to the staffed areas of Microforms & Newspapers and Interlibrary Loan (ILL).
Area location: southeast quadrant of the building
- Collections affected: PS92.02 - QC3.P35
- Faculty carrels affected: F201-F208