Workers planned to finish with those tiles and begin moving the pipe cutting equipment out of the Phase 3 area this afternoon.
The Phase 4 zone is in the southeast quadrant of the building. Its stacks area that is covered with plastic sheeting includes books with call numbers ranging from HQ1236.5 C2 W654 to LB1027.55 E73. Faculty carrels affected: F301-F308The transition from one area to the next this time took place a full week ahead of schedule, which means the sprinkler installation work is now moving very fast and much faster than in any previous phase. There were still issues with clearly communicating that the crews would be making an early switch, and this will be addressed in construction meetings. However, having the work done a lot faster than expected is a better problem than what the library experienced with the same work on, say, its 4th floor, where long delays were the norm.
After the work in Phase 4 on the 3rd floor is complete, the sprinkler system installation will move on to the 2nd floor, likely in just a couple of weeks.
No comments:
Post a Comment